132 building permits since 2015 in Cleveland city, OH and York township, OH, across 2 counties — $1,280,968 in reported job value over 132 permits that state one.
- Building permits
- 132
- Reported job value
- $1.3M
- Active
- 2015–2020
- Latest permit
- Nov 20, 2020
Where it works
Counties shaded by permits filed there; the dashed outline encloses every permit location.
Busiest jurisdictions
- Cleveland city, OH131
- York township, OH1
Permits by year
By issue date (application date where there is none).
View as tableHide table
| Year | Permits |
|---|---|
| 2015 | 30 |
| 2016 | 22 |
| 2017 | 30 |
| 2018 | 22 |
| 2019 | 19 |
| 2020 | 9 |
Type of work
Permits describing each kind of work; one permit can cover several.
- Demolition131
- Grading & excavation126
Permit types
As the building departments classify them.
- Demolition131
- DECK1
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Nov 20, 2020 | Demolition | 2 1/2 story, frame house, approx 884 sq ft, to be demolished. RAZE 2 1/2 STORY FRAME 1 D/U. REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE.CONTROL DUST P | Cleveland City | $7,956 |
| Oct 21, 2020 | Demolition | 2 story frame house- approx 1,159 sq ft, and garage, to be demolished. RAZE 2 STORY FRAME 1 D/U & GARAGE TO CORRECT COND. VN DATED 10/15/019. REMOVE ALL DEBRIS | Cleveland City | $8,241 |
| Oct 21, 2020 | Demolition | 2 1/2 story frame house- approx 1,020 sq ft, to be demolished .RAZE 2 1/2 STORY FRAME 1 D/U TO CORRECT COND. VN DATED 12/102018. REMOVE ALL DEBRIS FROM SITE. FI | Cleveland City | $7,803 |
| Oct 21, 2020 | Demolition | RAZE 2 STORY FRAME 2 DU. REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE. CONTROL DUST PER 277.07. SEED LOT AND REMOVE ALL FOUNDATION. DISCONTINUE AND CAP | Cleveland City | $7,819 |
| Jun 16, 2020 | Demolition | RAZE 1 1/2 STORY FRAME 1 DU AND GARAGE TO CORRECT CONDEMNATION VN DATED 4/14/2016 V16013093 REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE. CONTROL DUST | Cleveland City | $8,265 |
| May 4, 2020 | Demolition | RAZE 2 1/2 STORY FRAME 2 DU. REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE. CONTROL DUST PER 277.07. SEED LOT AND REMOVE ALL FOUNDATION. DISCONTINUE AND | Cleveland City | $10,242 |
| Mar 4, 2020 | Demolition | RAZE 1.5 STORY FRAME 1 DU. REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE. CONTROL DUST PER 277.07. SEED LOT. REMOVE ALL FOUNDATIONS. DISCONTINUE & CAP U | Cleveland City | $8,574 |
| Mar 4, 2020 | Demolition | RAZE 2.5 STORY FRAME 1 DU & GARAGE TO CORRECT COND VN DT 2-12-2018.. REMOVE ALL DEBRIS FROM SITE. FILL EXCAVATION TO GRADE. CONTROL DUST PER 277.07. SEED LOT. R | Cleveland City | $8,496 |
Permit status
Where its permits stand, as the departments report them.
- Approved104
- Closed24
- Issued2
- Pending2
Also on file as
Spellings on its permits, combined into this profile because they work the same area:
- THE BARKER GROUP LLC
- BARKER GROUP LLC
Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.