13 building permits since 2023 in Stamford town, CT; Rocky Hill town, CT and Stratford town, CT, across 3 counties — $330,369 in reported job value over 13 permits that state one.
- Building permits
- 13
- Reported job value
- $330.4K
- Active
- 2023–2026
- Latest permit
- Feb 26, 2026
Where it works
Counties shaded by permits filed there; the dashed outline encloses every permit location.
Busiest jurisdictions
- Stamford town, CT10
- Rocky Hill town, CT1
- Stratford town, CT1
- New Milford town, CT1
Permits by year
By issue date (application date where there is none).
View as tableHide table
| Year | Permits |
|---|---|
| 2023 | 2 |
| 2024 | 3 |
| 2025 | 5 |
| 2026 (YTD) | 3 |
Type of work
Permits describing each kind of work; one permit can cover several.
- Electrical12
- EV chargers10
- Bathrooms1
Permit types
As the building departments classify them.
- Electrical Permit8
- Building Permit5
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Feb 26, 2026 | Building Permit | Installing Level 2 chargers through out parking garages | Stamford Town | $92,000 |
| Feb 17, 2026 | Electrical Permit | Installing 200 amp service pedestal to feed four level two chargers, two at the entrance of parking garage & 2 in the ground level parking garage | Stamford Town | $18,000 |
| Feb 13, 2026 | Building Permit | Installing New 200 amp pedestal service to feed four level 2 chargers. There will be two chargers in front entrance to parking garage and two chargers inside gr | Stamford Town | $18,000 |
| Oct 23, 2025 | Electrical Permit | Installing 4 level 2 chargers in buildings 100 & 122 parking garage, fed from existing owners panels | Stamford Town | $14,000 |
| Jan 22, 2025 | Electrical Permit | Install two 200 amp Pedestal service's , four level 2 EV chargers two chargers per service Pole mounted. Total of two Charging poles, each pole having two charg | Stamford Town | $19,000 |
| Jan 15, 2025 | Building Permit | installing two - 200 amp service pedestals, each service will serve two level 2 evse's, pole mounted in parking lot area. Total of 4 ev chargers. | Stamford Town | $19,000 |
| Jan 6, 2025 | Building Permit | Installing three 200 amp service pedestals located in parking lots, to serve six Ev chargers. | Stamford Town | $28,000 |
| Jan 6, 2025 | Electrical Permit | Installing three 200 amp pedestal services, 6 EV chargers, bollards. Each 200 amp service will have two EV chargers mounted on a single pedestal. | Stamford Town | $28,000 |
Permit status
Where its permits stand, as the departments report them.
- Completed10
- Active3