Contractor · HVAC

BDL Environmental Consultants, Inc.

14 building permits since 2019 in New Milford town, CT; New Fairfield town, CT and Bethel town, CT — $36,920 in reported job value over 14 permits that state one.

Building permits
14
Reported job value
$36.9K
Active
2019–2026
Latest permit
Mar 12, 2026

Where it works

Counties shaded by permits filed there; the dashed outline encloses every permit location.

Permits by county, fewer to moreOperating area

Busiest jurisdictions

  • New Milford town, CT6
  • New Fairfield town, CT3
  • Bethel town, CT1
  • Brookfield town, CT1
  • Greenwich town, CT1
  • Norwalk town, CT1
  • Ridgefield town, CT1

Permits by year

By issue date (application date where there is none).

02.55
5
20192023202420252026*
* 2026 is year to date.
View as table
YearPermits
20191
20231
20244
20255
2026 (YTD)3

Type of work

Permits describing each kind of work; one permit can cover several.

  • HVAC10
  • Grading & excavation5
  • Additions1

Permit types

As the building departments classify them.

  • Mechanical Permit8
  • Miscellaneous Work Permit Application3
  • FUEL TANKS1
  • HV21
  • Mech Alt Comm1

Recent permits

The 8 newest on file.

DateTypeWorkJurisdictionJob value
Mar 12, 2026Mechanical PermitRemoval of previosuly cut and cleaned and abandonned 275 gallon #2 fuel oil UST. Sample tank grave and backfill to grade.New Milford Town$2,000
Jan 6, 2026Mechanical PermitAbandonment of (1) 550 gallon #2 fuel oil UST, located at the front right of house. Cut opening in top of tank, remove remaining sludges and piping, cut a hole New Milford Town$3,500
Jan 5, 2026Miscellaneous Work Permit ApplicationRemoval of (1) 550 gallon UST: Expose and cut opening in top of tank, clean interior of tank, remove tank from grave, sample soils in grave, backfill to grade.New Fairfield Town$2,625
Dec 1, 2025Mechanical PermitExcavate and expose top of tank, cut opening, clean tank via vac truck, remove tank from ground, take soil samples in tank grave, backfill to grade.Brookfield Town$2,400
Nov 12, 2025Mechanical PermitRemoval of (1) 550 gallon UST including cleaning of UST, removal of UST and piping and any old product, sample soils in UST grave and backfill to grade. DisposeNew Milford Town$2,500
Jul 18, 2025Miscellaneous Work Permit ApplicationRemoval of (1) 550 Gallon UST #2 fuel oil. Expose top of tank, cut opening, clean tank, remove tank & piping from ground, sample soils in grave, backfill to graNew Fairfield Town$2,950
Jul 15, 2025Mechanical PermitRemoval of (1) 275 gallon # 2 Fuel oil UST and associated piping.New Milford Town$1,950
Feb 21, 2025Mechanical PermitPump out and clean then excavate (1) 550 UST - #2 Fuel Oil - Sampling soils Backfill to gradeRidgefield Town$3,050

Permit status

Where its permits stand, as the departments report them.

  • Completed10
  • Active2
  • Issued1
  • Stop work ordered1

Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.