Contractor · Electrical

ROBERTS SAMUEL & ROBERTS MIRANDA

15 building permits since 2022 in Santa Cruz County, CA.

Building permits
15
Reported job value
—
Active
2022–2026
Latest permit
Jan 29, 2026

Where it works

Counties shaded by permits filed there.

Permits by county, fewer to more

Busiest jurisdictions

  • Santa Cruz County, CA15

Permits by year

By issue date (application date where there is none).

02.55
5
20222023202420252026*
* 2026 is year to date.
View as table
YearPermits
20221
20233
20245
20254
2026 (YTD)2

Type of work

Permits describing each kind of work; one permit can cover several.

  • HVAC3
  • Electrical3
  • Solar2
  • Battery storage2
  • Bathrooms2
  • EV chargers2
  • Fire sprinklers2
  • Generators1
  • Windows & doors1
  • New construction1

Permit types

As the building departments classify them.

  • Building15

Recent permits

The 8 newest on file.

DateTypeWorkJurisdictionJob value
Jan 29, 2026BuildingPermit extension granted #1 for permit B-261386. New expiration date is 7/28/26Santa Cruz County—
Jan 29, 2026BuildingPermit extension granted #1 for permit B-261387. New expiration date 7/28/26Santa Cruz County—
Jun 24, 2025Building110 Smith Rd, Watsonville CA 95076. Deferred Submittal # 1 to building permit B- 223586 for the following; Install an OFF-GRID roof mount (28.56)kW, (68) moduleSanta Cruz County—
Jun 11, 2025BuildingSITE ADDRESS: 110 Smith Rd, Watsonville, CA 95076 Deferred Submittal # 1 to building permit B-223588 for the following; Install an OFF-GRID roof mount (11.34)kWSanta Cruz County—
Apr 18, 2025BuildingConstruction Change Document #2 to Permit B-223586 to include, update mechanical plan, folding doors instead of sliding doors at residence, stone tile siding, HSanta Cruz County—
Jan 21, 2025BuildingConstruction Change Document #1 to Permit B-237985 to include: removal of EVCS from scope of work (deferred submittal).Santa Cruz County—
Oct 28, 2024BuildingChange Order (Construction Change Document) # 1 to building permit B-223586 for the following; Retaining wall detail at culvert.Santa Cruz County—
Sep 26, 2024BuildingDeferred Submittal # 1 to building permit B-237985 for the following ; Form PLG290 - Electrical Vehicle Charging station load calculations forms.Santa Cruz County—

Permit status

Where its permits stand, as the departments report them.

  • Completed14
  • Not stated1