Contractor · Electrical
Lindsey Governali
17 building permits since 2017 in Stamford town, CT and Stratford town, CT, across 2 counties — $2,619,161 in reported job value over 17 permits that state one.
- Building permits
- 17
- Reported job value
- $2.6M
- Active
- 2017–2018
- Latest permit
- Jun 14, 2018
Where it works
Counties shaded by permits filed there; the dashed outline encloses every permit location.
Busiest jurisdictions
- Stamford town, CT16
- Stratford town, CT1
Permits by year
By issue date (application date where there is none).
View as tableHide table
| Year | Permits |
|---|---|
| 2017 | 11 |
| 2018 | 6 |
Type of work
Permits describing each kind of work; one permit can cover several.
- Electrical14
- Windows & doors2
Permit types
As the building departments classify them.
- Building Permit9
- Electrical Permit8
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Jun 14, 2018 | Electrical Permit | Installing 2 new elevators | Stratford Town | $4,000 |
| May 9, 2018 | Building Permit | Installing (1) elevator as subcontractor for JA Rosa Construction LLC. ***MADE INACTIVE*** We cannot accept application because you applied with the wrong appli | Stamford Town | $144,900 |
| Mar 15, 2018 | Building Permit | Modernizing (2) Escalators. | Stamford Town | $744,000 |
| Mar 15, 2018 | Electrical Permit | Modernizing (2) Escalators. I included the cost of the electrical work ($2,000) in the building permit application (TB-18-464). | Stamford Town | $2,000 |
| Jan 18, 2018 | Building Permit | Installing (4) EcoSpace elevators. ***MADE INCOMPLETE*** This application has been made incomplete because you applied with the wrong application. The Elevators | Stamford Town | $554,800 |
| Jan 18, 2018 | Electrical Permit | Installing (4) Ecospace elevators. Cost of electrical was already included in Building Permit application (TB-18-121). | Stamford Town | $8,000 |
| Nov 6, 2017 | Electrical Permit | Installing (1) EcoSpace Elevator. GC provides us power, we just hook up our wiring for the elevator. **FYI - Building permit application # TB-17-2037 INCLUDES t | Stamford Town | $2,000 |
| Nov 3, 2017 | Building Permit | Installing (1) EcoSpace Elevator ***MADE INCOMPLETE*** We cannot accept this application because you need to apply for an Electrical Permit and provide the Agen | Stamford Town | $95,500 |
Permit status
Where its permits stand, as the departments report them.
- Active13
- Completed4
Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.