Contractor · Demolition & excavation
KUNEY, MAX J CO Austin Miller
19 building permits since 2017 in Bellevue city, WA.
- Building permits
- 19
- Reported job value
- —
- Active
- 2017–2019
- Latest permit
- Nov 1, 2019
Where it works
Counties shaded by permits filed there.
Busiest jurisdictions
- Bellevue city, WA19
Permits by year
By issue date (application date where there is none).
07.515
11
201720182019
View as tableHide table
| Year | Permits |
|---|---|
| 2017 | 4 |
| 2018 | 11 |
| 2019 | 4 |
Type of work
Permits describing each kind of work; one permit can cover several.
- Generators5
- Grading & excavation4
- Gas3
- HVAC1
- Remodels1
- Plumbing1
- Demolition1
- Windows & doors1
Permit types
As the building departments classify them.
- TK14
- BF5
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Nov 1, 2019 | TK | **EXTENDED to Jun 30... **EXTENDED to Apr 30 - again... **EXTENDED to Feb 28 - still waiting... **EXTENDED to Jan 31 -- waiting for weather window to complete. | Bellevue City | — |
| Oct 18, 2019 | TK | Opening of NE Spring Blvd to 2 way traffic between 132nd and 134th with turnaround area allowing construction of Spring blvd to continue East from 134th | Bellevue City | — |
| Mar 14, 2019 | TK | **EXTENDED to Nov 30, 2019. tjs 10/01/19** **EXTENDED to Sept 30, 2019. tjs 08/07/19** Night closures of NE Spring Blvd near 136th PL NE to facilitate installat | Bellevue City | — |
| Jan 18, 2019 | TK | Flagging for truck loading and haul out of excavation on 124th Ave NE | Bellevue City | — |
| Nov 19, 2018 | TK | Shift of Traffic on NE 20th to the south side of the roadway while reducing NE 20th to 1 lane in each direction for installation of Water Lines and Gas line low | Bellevue City | — |
| Sep 28, 2018 | TK | Flagging on NE Spring Blvd between 134th ave NE and 136th PL NE to facilitate excavation and setting of the EL 307 vault | Bellevue City | — |
| Sep 18, 2018 | TK | Partial implementation of approved MOT (Phase 1) at NE 20th St/136th Pl NE. Temp signal heads (including ped heads) will be installed, along with temp pedestria | Bellevue City | — |
| May 25, 2018 | TK | **EXTENDED TO Oct 31, 2019 with CONDITIONS (see P.I. REV 1). tjs 09/04/19** Closure of NE Spring Blvd between 132nd Ave NE and 134th Ave NE for utility install, | Bellevue City | — |
Permit status
Where its permits stand, as the departments report them.
- Closed8
- Expired8
- Cancelled3
Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.