Contractor · Electrical
Michael G. Kennedy
21 building permits since 2023 in Brunswick County, NC — $35,348,538 in reported job value over 21 permits that state one.
- Building permits
- 21
- Reported job value
- $35.3M
- Active
- 2023–2024
- Latest permit
- Mar 25, 2024
Where it works
Counties shaded by permits filed there.
Busiest jurisdictions
- Brunswick County, NC21
Permits by year
By issue date (application date where there is none).
07.515
15
20232024
View as tableHide table
| Year | Permits |
|---|---|
| 2023 | 15 |
| 2024 | 6 |
Type of work
Permits describing each kind of work; one permit can cover several.
- Plumbing6
- Electrical6
- Roofing3
- New construction3
Permit types
As the building departments classify them.
- BUILDING3
- EMERGENCY RESPONDER RADIO COVERAGE3
- FIRE PERMIT3
- FOUNDATION ONLY3
- PRIOR POWER RELEASE3
- TEMPORARY CO3
- BUILDING (MINIMUM)1
- GATE AND BARRICADE ACROSS FIRE APPARATUS1
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Mar 25, 2024 | TEMPORARY CO | Open for business 90 day TCO Projected completion date: June 20 2024 Requesting a temporary certificate of occupancy for a period of 90 days. Fire inspection fa | Brunswick County | $1,540,546 |
| Mar 25, 2024 | TEMPORARY CO | Open for business 90 day TCO Projected completion date: June 20 2024 Requesting a temporary certificate of occupancy for a period of 90 days. Fire inspection fa | Brunswick County | $1,310,002 |
| Mar 25, 2024 | TEMPORARY CO | Open for business 90 day TCO Projected completion date: June 20 2024 Requesting a temporary certificate of occupancy for a period of 90 days. Fire inspection fa | Brunswick County | $2,309,026 |
| Mar 7, 2024 | PRIOR POWER RELEASE | Temporary electric: 60 days Requesting temporary electric for all circuits in the building. Power to building so that lights can be turned to finish the interio | Brunswick County | $1,540,546 |
| Mar 6, 2024 | PRIOR POWER RELEASE | Temporary electric: 60 days Requesting temporary electric for all circuits in the building. Power to building so that lights can be turned to finish the interio | Brunswick County | $2,309,026 |
| Feb 22, 2024 | PRIOR POWER RELEASE | Temporary electric. 60 days All circuits for building #3. Power to building so that lights can be turned on to finish the inside portion of the building. There | Brunswick County | $1,310,002 |
| Dec 27, 2023 | BUILDING | New Commercial Structure • Intended Use : Storage Unit Facility • Sq Ft Not Under Roof : 28 • Sq Ft Under Roof : 12000 • Stories : 1 • Units : 64 • Number of Em | Brunswick County | $1,540,546 |
| Dec 27, 2023 | BUILDING | New Commercial Structure • Intended Use : Storage Unit Facility • Sq Ft Not Under Roof : 28 • Sq Ft Under Roof : 18000 • Stories : 1 • Units : 142 • Number of E | Brunswick County | $2,309,026 |
Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.