Contractor · HVAC
VERIZON PENNSYLVANIA, INC
22 building permits since 2001 in Bethel Park municipality, PA.
- Building permits
- 22
- Reported job value
- —
- Active
- 2001–2013
- Latest permit
- Jan 2, 2013
Where it works
Counties shaded by permits filed there; the dashed outline encloses every permit location.
Busiest jurisdictions
- Bethel Park municipality, PA22
Permits by year
By issue date (application date where there is none).
0510
10
200120082009201020122013
View as tableHide table
| Year | Permits |
|---|---|
| 2001 | 1 |
| 2008 | 6 |
| 2009 | 10 |
| 2010 | 3 |
| 2012 | 1 |
| 2013 | 1 |
Type of work
Permits describing each kind of work; one permit can cover several.
- HVAC20
- Telecom18
Permit types
As the building departments classify them.
- PAVED - OPENING21
- UNPAVED - OPENING1
Recent permits
The 8 newest on file.
| Date | Type | Work | Jurisdiction | Job value |
|---|---|---|---|---|
| Jan 2, 2013 | PAVED - OPENING | PURPOSE - DIRECTIONAL BORE 9,387' OF 1.25" PLASTIC DUCT INCLUDING 25 ROAD CROSSING AND 64 TERMINAL VAULTS. NEW FACILITIES WILL FOLLOW EXISTING COPPER PATH AND W | Bethel Park | — |
| Feb 15, 2012 | PAVED - OPENING | PURPOSE: PLACE 402' OF BURIED (BORED) 1.25" PLASTIC DUCT INCLUDING 2 2'X3' OPENINGS FOR TERMINAL VAULTS. VAULTS WILL BE FLUSH MOUNTED. FIOS SERVICE PROVISIONING | Bethel Park | — |
| Mar 12, 2010 | PAVED - OPENING | PURPOSE: PLACE 1346' BURIED 1.25" PLASTIC DUCT FOR FIBER OPTIC CABLE INCLUDING 3 ROAD CROSSINGS AND 11 VAULTS FOR TERMINALS TO UPGRADE THE TELECOMMUNICATIONS NE | Bethel Park | — |
| Jan 25, 2010 | PAVED - OPENING | PURPOSE: PLACE 860' BURIED 1.25" PLASTIC DUCT FOR FIBER OPTIC CABLE INCLUDING 1 ROAD CROSSINGS AND 4 VAULTS FOR TERMINALS TO UPGRADE THE TELECOMMUNCIATIONS NETW | Bethel Park | — |
| Jan 5, 2010 | PAVED - OPENING | PURPOSE: PLACE 1,380' BURIED 1`.25" PLASTIC DUCT FOR FIBER OPTIC CABLE INCLUDING 3 ROAD CROSSINGS AND 10 VAULTS FOR TERMINALS TO UPGRADE THE TELECOMMUNICATIONS | Bethel Park | — |
| Dec 8, 2009 | PAVED - OPENING | PURPOSE: PACE 1 30' POLE AT THE CORNER OF OAKLYN ROAD & EASTVIEW ROAD 4' AWAY FROM BOTH ROADS IN THE PUBLIC ROW. THE HOLE WILL BE APPROXIMATELY 2' X 2' X 5 1/2' | Bethel Park | — |
| Oct 15, 2009 | PAVED - OPENING | PURPOSE: PLACE 2,572' BURIED 1.25" PLASTIC DUCT FOR FIBER OPTIC CABLE INCLUDING 9 ROAD CROSSINGS AND 27 VAULTS FOR TERMINALS TO UPGRADE THE TELECOMMUNICATIONS N | Bethel Park | — |
| Apr 20, 2009 | PAVED - OPENING | PURPOSE; PLACE 2670' BURIED 1.25" PLASTIC DUCT FOR FIBER OPTIC CABLE INCLUDING 2 ROAD CROSSINGS AND 11 VAULTS FOR TERMINALS TO UPGRADE THE TELECOMMUNICATIONS NE | Bethel Park | — |
Permit status
Where its permits stand, as the departments report them.
- Active21
- Not stated1
Compiled from public building permit records. A contractor here is the name on the permits, with spelling variants combined where they work the same area; the same name in distant markets is listed separately. Job values are as reported on the permits.